EPA: xAI’s Colossus data center illegally used gas turbines without permits
The Environmental Protection Agency has ruled that xAI violated the law when it used dozens of portable gas generators for its Colossus 1 data center without air quality permits.
When xAI set out to build Colossus 1 in Memphis, Tennessee, CEO Elon Musk wanted to move with unprecedented speed, avoiding all of the red tape that could slow such a big project down.
To power the 1-gigawatt data center, Musk took advantage of a local loophole that allowed portable gas generators to be used without any permits, as long as they did not spend more than 364 days in the same spot. That allowed xAI to bring in dozens of truck-sized gas generators to quickly supply the massive amount of power the data center needed to train xAI’s Grok model.
The new EPA rule says the use of such portable generators falls under federal regulation, and the company did need air quality permits to operate the turbines. xAI is also using dozens of such generators to power its Colossus 2 data center just over the border in Alabama.
To power the 1-gigawatt data center, Musk took advantage of a local loophole that allowed portable gas generators to be used without any permits, as long as they did not spend more than 364 days in the same spot. That allowed xAI to bring in dozens of truck-sized gas generators to quickly supply the massive amount of power the data center needed to train xAI’s Grok model.
The new EPA rule says the use of such portable generators falls under federal regulation, and the company did need air quality permits to operate the turbines. xAI is also using dozens of such generators to power its Colossus 2 data center just over the border in Alabama.